Haryana RERA: Homebuyers Can Claim Delay Interest, Not Additional Compensation for the Same Delay

Haryana RERA delay interest ruling in the ATS Triumph delayed possession case in Gurugram

Haryana RERA has clarified that home-buyers who choose to remain in a delayed housing project can claim interest for the possession delay, but they cannot demand additional compensation for the same delay after the authority has already awarded interest. The latest ruling concerns two Delhi home-buyers who sought ₹91 lakh in compensation from the developer of ATS Triumph in Gurugram.

On 11 November 2026, Haryana RERA adjudicating officer Rajender Kumar dismissed their compensation complaint. The officer referred to Section 18(1) of the Real Estate (Regulation and Development) Act, 2016, and earlier tribunal rulings to explain the distinction between delay interest and compensation.

The decision highlights an important aspect of Haryana’s real estate regulations and offers useful guidance to home-buyers dealing with delayed possession.

Haryana RERA Rejects ₹91 Lakh Compensation Claim in ATS Triumph Case

The case involves Dr. Renu Srivastav and Col. (Dr.) Ashwini Goel (Retd.), who purchased unit 6031 in Tower 6 of the ATS Triumph project in Gurugram.

The couple signed their agreement with Anand Divine Developers on 27 March 2018. They booked the apartment for approximately ₹1.9 crore and eventually paid around ₹2.2 crore, including a ₹1.56 crore loan from Punjab National Bank.

However, the buyers faced delays in receiving possession. Consequently, they approached Haryana RERA and sought financial relief for the delay.

The authority had already decided their delayed-possession complaint on 28 September 2023 and awarded interest at 10.7% per annum.

Later, the buyers approached the adjudicating officer and sought approximately ₹91 lakh in additional compensation under several categories.

However, the officer dismissed their latest complaint because the authority had already awarded interest for the same possession delay.

Haryana RERA Delay Interest: What the Latest Ruling Says

The buyers sought compensation under several heads, including:

  • ₹45.4 lakh with 18% interest
  • ₹1.2 lakh per month towards rental expenses
  • ₹25 lakh for mental harassment
  • ₹10 lakh under Section 72(a)
  • ₹10 lakh under Section 14
  • ₹55,000 towards litigation costs

However, the adjudicating officer concluded that the buyers could not claim additional damages for the same delay after the authority had already awarded delayed-possession interest.

The developer, Anand Divine Developers, argued that it had offered possession in May 2019. It also stated that the buyers took physical possession on 19 March 2022.

Furthermore, the officer examined the buyers’ allegations concerning carpet area, terrace area, imported wooden flooring, electricity meter installation, seepage and incomplete paintwork.

However, the buyers had not raised these issues before the authority during their earlier proceedings. Therefore, the officer declined to entertain those allegations in the subsequent complaint.

How Haryana RERA Delay Interest Works Under Section 18

Section 18(1) of the Real Estate (Regulation and Development) Act, 2016, explains the remedies available to home-buyers when a developer fails to deliver possession within the agreed timeline.

The provision establishes two important situations:

1. When a home-buyer withdraws from the project

If a developer fails to deliver possession within the agreed timeline, the buyer can withdraw from the project and seek a refund along with prescribed interest and applicable compensation under the Act.

2. When a home-buyer chooses to stay in the project

If the buyer decides to continue with the project, the developer must pay interest for every month of delay until it hands over possession.

Therefore, the law distinguishes between buyers who exit a delayed project and buyers who continue with their investment.

In the ATS Triumph case, the couple chose to remain in the project and had already received an order granting 10.7% annual interest for the delay. Consequently, the adjudicating officer rejected their additional compensation claim for that same delay.

Earlier Haryana RERA Decisions Support This Interpretation

The latest ATS Triumph ruling follows an interpretation that Haryana RERA has applied in earlier cases.

For instance, in August 2025, the authority dismissed an additional compensation claim filed by a home-buyer against BPTP Limited and Countrywide Promoters Pvt. Ltd. in the Mansions Park Prime project, Sector 66, Gurugram.

In that case, the authority had already awarded interest at 10.45% per annum for the possession delay. Later, the buyer sought additional compensation for rental expenses, mental harassment, depreciation and other losses.

However, the authority concluded that a buyer who chooses to remain in a project can claim delay interest under Section 18(1), rather than additional compensation for the same delay.

Similarly, in December 2024, Haryana RERA dismissed another additional compensation complaint against Emaar MGF Land Limited concerning Emerald Estate in Sector 65, Gurugram. The authority had previously awarded interest at 10.75% per annum for the delay.

These decisions demonstrate how the authority has distinguished between delay interest for buyers who remain in projects and refund-related remedies for buyers who withdraw.

What the Haryana RERA Delay Interest Ruling Means for Buyers

The latest Haryana RERA ruling highlights the importance of understanding the available legal remedies before filing a complaint.

Home-buyers should consider the following points:

Check your possession agreement: First, review the possession deadline and the terms of your builder-buyer agreement.

Understand your Section 18 rights: Next, decide whether you want to continue with the project or withdraw and seek a refund, depending on your circumstances and applicable legal rights.

Maintain payment records: Keep copies of payment receipts, bank statements, demand letters and communication with the developer.

Raise separate violations properly: If you face issues such as incorrect area specifications, missing amenities, construction defects or other regulatory violations, document them and raise them through the appropriate proceedings.

Review previous RERA orders: Finally, examine any earlier order concerning your project or complaint before filing another case. This step can help you avoid overlapping claims and strengthen your case.

Importantly, the ATS Triumph decision does not establish that buyers lose every other legal remedy after accepting possession. It addresses additional compensation for the same delay and the specific allegations that the buyers had not raised in their earlier proceedings.

Does This Ruling Change the Position for Gurugram Home-buyers?

The latest decision reinforces the distinction between delay interest and additional compensation under the RERA framework.

For buyers who want to remain in a delayed project, the ruling highlights the importance of pursuing the prescribed interest remedy. Meanwhile, buyers who want to exit a project can examine their refund and compensation rights under Section 18(1), subject to the applicable legal conditions.

However, home-buyers should not treat this order as a blanket restriction on all compensation claims. Independent violations, contractual disputes and other statutory claims may require separate examination.

A notable development also came from the Punjab and Haryana High Court in October 2026. The court ruled that accepting possession or executing a conveyance deed does not, by itself, remove a buyer’s statutory right to claim interest for delayed possession. At the same time, the court discussed reasonable time limits for filing such complaints.

Therefore, home-buyers should distinguish between the right to claim statutory delay interest and the right to seek additional damages for the same delay.

Expert Perspective: Sanjeev Singh, MD, SKJ Landbase

Haryana RERA delay interest ruling in the ATS Triumph delayed possession case in Gurugram
Haryana RERA rejects a ₹91 lakh additional compensation claim in the ATS Triumph case and clarifies the rights of buyers who stay in delayed projects.

Sanjeev Singh says that the latest Haryana RERA decision reinforces the importance of understanding legal rights before making a real estate investment. Home-buyers should carefully examine possession timelines, payment schedules, builder-buyer agreements and project approvals before committing their money.

He also highlights that buyers should maintain proper documentation throughout their property journey. When a developer delays possession or fails to meet contractual obligations, buyers should understand the remedies available under RERA and seek appropriate legal guidance before filing a complaint.

Conclusion

The latest Haryana RERA ruling in the ATS Triumph case establishes an important distinction between delay interest and additional compensation.

The adjudicating officer rejected the ₹91 lakh claim filed by two Delhi home-buyers because the authority had already awarded them 10.7% annual interest for the possession delay.

Consequently, the decision reinforces the interpretation that buyers who remain in delayed projects can claim prescribed interest for the delay, but cannot demand additional damages for that same delay under the circumstances examined in this case.

For Gurugram home-buyers, the key takeaway remains clear: understand your rights under Section 18(1), maintain proper documentation and raise every relevant grievance through the appropriate legal proceedings.